VOLTA Engineering – Phase I.
Industrial segment: Metal industry, Automotive industry
Location: Környe, Hungary
Time period: 6 months
Resources: 8 project managers (for 120-150 construction workers), 14 logistic and mechanical workers
Short Descripiton:
Project Management, assembly management and installation services for piping and equipment installation project in Phase 1 and Phase 2 for a metal industry production company.
VOLTA Engineering – Phase II.
Industrial segment: Metal industry, Automotive industry
Location: Környe, Hungary
Time period: 6 months
Resources: 8 project managers (for 120-150 construction workers), 14 logistic and mechanical workers
Short description:
Project Management, assembly management and installation services for piping and equipment installation project in Phase 1 and Phase 2 for a metal industry production company.
Toyoink
Industrial segment: Chemical industry
Location: Újhartyán, Hungary
Time period: 4 months
Resources: 1 project managers and 4 mechanical workers
Short Descripiton:
Building detail design and implementation of the extraction system expansion.
APOLLO
Industrial segment: Tyre industry
Location: Gyöngyöshalász, Hungary
Time period: 5 months
Resources: 1 project manager, 2 IT programmer and 8 electrical and mechanical workers
Short description:
CE conformity engineering services (Project Management, technology transfer, mechanical and electrical corrections, programming, commissioning, operation and maintenance guide document’s preparation) for rubber bale cutting for a tyre production plant of Apollo.
World Technical Solution
Industrial segment: Chemical industry, recycling, energy
Location: EU and Africa
Time period: ongoing project
Resources: 5 engineers, 2 economists and specialised experts
Short description:
Engineering services for the technical solutions required for the development, design and installation of equipment for the chemical recycling of plastics by World Technical Solution Ltd. Performing energetic analyses, economic calculations, and power plant simulations regarding the utilization of the products of the process.